BEAUCHAMP SIXTH FORM BPE- LEICESTER

Beauchamp Sixth Form College was opened for pupils in September 2020 as the latest addition to the Lionheart-Academy Trust in Leicester.

 

Beauchamp (pronounced Beecham) forms one of ISGs ESFA Lot 4 – Medium Value Band: East Midlands framework schools on the £8 billion programme of works for new build and refurbishment schools and colleges projects across England.

Now occupancy has been achieved for this conversion of a former HQ for British Telecom to a new Sixth Form College, ISG’s duty of care to the school continues with what is called a Building Performance Evaluation or BPE.  The BPE requires Ollio as ISG's BPE specialist to conduct a lessons learnt review of user’s feeling about their new building and its technical performance.

 

The review follow’s the guidance contained in the UK Government Department for Education's Priority Schools Building Programme specification Appendix G.

 

Building Performance Evaluation are short format Post Occupancy Evolutions.  The process commences with a visit to the school to meet with the contractors team and the head teacher's team to discuss how the project went, and unpack what residual issues might still need to be addressed.  After an introductory review meeting with the whole team at the Beauchamp site, we toured the building to look in more detail at what was happening on the ground and how the school was being used close up. 

We also issued two questionnaires, one to teachers and one to the facilities team to get a snapshot of users perception about what is good and maybe not so good. All done in a positive spirit of learning.

We also looked at energy use, comfort and indoor air quality, making sure it is being recorded correctly.  

Within ten days of the first visit we produced a report with proposed early interventions which were implemented by the headteacher and facilities teams

After six months we went back to Beauchamp to check how things were, how lessons are being learnt and if any more needs to be done to optimise energy use and user delight.

PROJECT DETAILS

Client : ISG Group

Construction Value: £10 million

Date: September 2020

Floor Area: 13,000m2

KEY FEATURES

  • Conversion of 13,000m2 office to new 1100 Pupil Sixth Form College.

  • Optimised existing heating and full ventilation strategy

  • Identified lessons learnt in DfE specifications for SEN 

  • Optimised energy use savings.

IMG_20210218_132550.jpg

Beauchamp Main Entrance

MORE POE CASE STUDIES

IMG_20201201_142850.jpg
Churchward SEND School

BPE for new SEND school in Swindon

IMG_20210419_125554_edited.jpg
Badbury Park Primary

BPE for new Primary School in Swindon

bottom of page